[Civil & Real Estate] Defense Against KRW 200M Construction Claim
페이지 정보
최고관리자 작성일26-10-27본문
Case Type: Civil Litigation (Defense Against Construction Cost Claim)
Result: Entire Claim Dismissed (Full Victory for Defendant, Legal Costs Borne by Plaintiff)
Case Detail:
1. Background and Plaintiff's Claim
This dispute arose from a multi-tiered subcontracting structure where the main contractor awarded a portion of new construction work to the Defendant (our client), the Defendant subcontracted it in writing to Company A, and Company A re-subcontracted it to the Plaintiff. Despite having no direct contractual agreement with the Defendant, the Plaintiff, who performed the actual work on-site, filed a lawsuit demanding over KRW 200 million in construction fees from the Defendant. The Plaintiff asserted that Company A was merely a nominal party inserted to bypass statutory restrictions on re-subcontracting, claiming that the Defendant was the actual contractual party based on identical itemized estimates and pre/post-construction settlement discussions with the Defendant's personnel.
2. Defense Strategy
The critical issue in this case was the identification of the contractual party. Representing the Defendant, Suhn Law Group focused on establishing that the Plaintiff was not a party to the contract, as construction fee claims can only be raised between direct contracting parties. We highlighted that there was no counter-evidence to refute the disposition document (written agreement) executed between the Defendant and Company A. Furthermore, we argued that claiming to perform KRW 1 billion worth of work without any written agreement contradicts common business practices, emphasizing that all contract-related documents submitted by the Plaintiff designated Company A as the recipient, not the Defendant.
3. Evidence Reinforcement and Judgment
To solidify the factual matrix, we secured and submitted a written confirmation from Company A regarding the contract execution process and obtained consistent testimony through witness examination. Convinced by our defense, the court ruled that the evidence was insufficient to recognize the Plaintiff as a contractual party. Consequently, the court dismissed all of the Plaintiff's claims without needing to review further issues and ordered the Plaintiff to bear all litigation costs.
Case Inquiry: Attorney SHIN, Joon sun